Configuration Management Policy
Fox and Geese standardizes and automates configuration management through the
use of Chef/Salt scripts as well as documentation of all changes to production
systems and networks. Chef and Salt automatically configure all Fox and Geese
systems according to established and tested policies, and are used as part of
our Disaster Recovery plan and process.
Applicable Standards
Applicable Standards from the HITRUST Common Security Framework
- 06 - Configuration Management
Applicable Standards from the HIPAA Security Rule
- 164.310(a)(2)(iii) Access Control & Validation Procedures
Configuration Management Policies
- Chef and Salt are used to standardize and automate configuration management.
- No systems are deployed into Fox and Geese environments without approval of
the Fox and Geese CTO.
- All changes to production systems, network devices, and firewalls are
approved by the Fox and Geese CTO before they are implemented to assure they
comply with business and security requirements.
- All changes to production systems are tested before they are implemented in
production.
- Implementation of approved changes are only performed by authorized
personnel.
- Tooling to generate an up-to-date inventory of systems, including
corresponding architecture diagrams for related products and services, is
hosted on GitLab.
- All systems are categorized as production and utility to differentiate
based on criticality.
- The Security Officer maintains scripts to generate inventory lists on
demand using APIs provided by each cloud provider.
- These scripts are used to generate the diagrams and asset lists required by
the Risk Assessment phase of Fox and Geese's Risk Management procedures
(Risk Management Procedures).
- After every use of these scripts, the Security Officer will verify their
accuracy by reconciling their output with recent changes to production
systems. The Security Officer will address any discrepancies immediately
with changes to the scripts.
- All frontend functionality (developer dashboards and portals) is separated
from backend (database and app servers) systems by being deployed on separate
servers or containers.
- All software and systems are tested using unit tests and end to end tests.
- All committed code is reviewed using pull requests to assure software code
quality and proactively detect potential security issues in development.
- Fox and Geese utilizes development and staging environments that mirror
production to assure proper function.
- Fox and Geese also deploys environments locally using Vagrant to assure
functionality before moving to staging or production.
- All formal change requests require unique ID and authentication.
- Fox and Geese uses the
Security Technical Implementation Guides (STIGs)
published by the Defense Information Systems Agency as a baseline for
hardening systems.
- Windows-based systems use a baseline Active Directory group policy
configuration in conjunction with the Windows Server 2012 STIG.
- Linux-based systems use a Red Hat Enterprise Linux STIG which has been
adapted for Ubuntu and improved based on the results of subsequent
vulnerability scans and risk assessments.
- Clocks are continuously synchronized to an authoritative source across all
systems using NTP or a platform-specific equivalent. Modifying time data on
systems is restricted.
Provisioning Production Systems
- Before provisioning any systems, ops team members must file a request in the
Fox and Geese Quality Management System.
- Quality Management System access requires authenticated users.
- The CTO grants access to the Quality Management System following the
procedures covered in the Systems Access Policy.
- The CTO, or an authorized delegate of the CTO, must approve the provisioning
request before any new system can be provisioned.
- Once provisioning has been approved, the ops team member must configure the
new system according to the standard baseline chosen for the system's role.
- For Linux systems, this means adding the appropriate grains to the Salt
configuration file and running a
highstate
operation.
- For Windows systems, this means adding the appropriate roles to the
system's Chef profile and forcing a Chef run.
- If the system will be used to house production data (PHI or PII), the ops
team member must add an encrypted block data volume to the VM during
provisioning.
- For systems on AWS, the ops team member must add an encrypted Elastic Block
Storage (EBS) volume.
- For systems on other cloud providers, the ops team member must add a block
data volume and set up OS-level data encryption using Salt or Chef.
- Once the system has been provisioned, the ops team member must contact the
security team to inspect the new system. A member of the security team will
verify that the secure baseline has been applied to the new system, including
(but not limited to) verifying the following items:
- Removal of default users used during provisioning.
- Network configuration for system.
- Data volume encryption settings.
- Intrusion detection and virus scanning software installed.
- All items listed below in the operating system-specific subsections below.
- Once the security team member has verified the new system is correctly
configured, the team member must add that system to the Nessus security
scanner configuration.
- The new system may be rotated into production once the CTO verifies all the
provisioning steps listed above have been correctly followed and has marked
the Issue with the
Approved
state.
Provisioning Linux Systems
- Linux systems have their baseline security configuration applied via Salt
states. These baseline Salt states cover:
- Ensuring that the machine is up-to-date with security patches and is
configured to apply patches in accordance with our policies.
- Stopping and disabling any unnecessary OS services.
- Installing and configuring the OSSEC IDS agent.
- Configuring 15-minute session inactivity timeouts.
- Installing and configuring the ClamAV virus scanner.
- Installing and configuring the NTP daemon, including ensuring that
modifying system time cannot be performed by unprivileged users.
- Configuring LUKS volumes for providers that do not have native support for
encrypted data volumes, including ensuring that encryption keys are
protected from unauthorized access.
- Configuring authentication to the centralized LDAP servers.
- Configuring audit logging as described in the
Auditing Policy.
- Any additional Salt states applied to the Linux system must be clearly
documented by the ops team member in the DT request by specifying the purpose
of the new system.
Provisioning Windows Systems
- Windows systems have their baseline security configuration applied via the
combination of Group Policy settings and Chef recipes. These baseline
settings cover:
- Joining the Windows Domain Controller and applying the Active Directory
Group Policy configuration.
- Ensuring that the machine is up-to-date with security patches and is
configured to apply patches in accordance with our policies.
- Stopping and disabling any unnecessary OS services.
- Installing and configuring the OSSEC IDS agent.
- Configuring 15-minute session inactivity timeouts.
- Installing and configuring the Avast virus scanner.
-
- Configuring transport encryption according to specified requirements.
- Configuring the system clock, including ensuring that modifying system time
cannot be performed by unprivileged users.
- Configuring audit logging as described in the
Auditing Policy.
- Any additional Salt states applied to the Linux system must be clearly
documented by the ops team member in the DT request by specifying the purpose
of the new system.
Provisioning Management Systems
- Provisioning management systems such as Salt servers, LDAP servers, or VPN
appliances follows the same procedure as provisioning a production system.
- Provisioning the first Salt server for a production pod requires
bootstrapping Salt. An authorized member of the Dev Ops team will oversee
provisioning a new Salt server.
- Once the Salt server has been bootstrapped, the ops team member will apply
the baseline configuration to the Salt server by performing a
highstate
operation as usual.
- Critical infrastructure services such as logging, monitoring, LDAP servers,
or Windows Domain Controllers must be configured with appropriate Salt
states.
- These Salt states have been approved by the CTO, or an authorized delegate
of the CTO, to be in accordance with all Fox and Geese policies, including
setting appropriate:
- Audit logging requirements.
- Password size, strength, and expiration requirements.
- Transmission encryption requirements.
- Network connectivity timeouts.
- Critical infrastruture roles applied to new systems must be clearly
documented by the ops team member in the DT request.
Changing Existing Systems
- Subsequent changes to already-provisioned systems are unconditionally handled
by one of the following methods:
- Changes to Salt states or pillar values.
- Changes to Chef recipes.
- For configuration changes that cannot be handled by Chef or Salt, a runbook
describing exactly what changes will be made and by whom.
- Configuration changes to Chef recipes or Salt states must be initiated by
creating a Merge Request in GitLab.
- The ops team member will create a feature branch and make their changes on
that branch.
- The ops team member must test their configuration change locally when
possible, or on a development and/or staging sandbox otherwise.
- At least one other ops team member must review the Chef or Salt change
before merging the change into the main branch.
- In all cases, before rolling out the change to production, the ops team
member must file an Issue in the DT project describing the change. This Issue
must link to the reviewed Merge Request and/or include a link to the runbook.
- Once the request has been approved by the CTO, the ops team member may roll
out the change into production environments.
Patch Management Procedures
- Fox and Geese uses automated tooling to ensure systems are up-to-date with
the latest security patches.
- On Ubuntu Linux systems, the unattended-upgrades tool is used to apply
security patches in phases.
- The security team maintains a mirrored snapshot of security patches from
the upstream OS vendor. This mirror is synchronized bi-weekly and applied
to development systems nightly.
- If the development systems function properly after the two-week testing
period, the security team will promote that snapshot into the mirror used
by all staging systems. These patches will be applied to all staging
systems during the next nightly patch run.
- If the staging systems function properly after the two-week testing period,
the security team will promote that snapshot into the mirror used by all
production systems. These patches will be applied to all production systems
during the next nightly patch run.
- Patches for critical kernel security vulnerabilities may be applied to
production systems using hot-patching tools at the discretion of the
Security Officer. These patches must follow the same phased testing process
used for non-kernel security patches; this process may be expedited for
severe vulnerabilities.
- On Windows systems, the baseline Group Policy setting configures Windows
Update to implement the patching policy.
Software Development Procedures
- All development uses feature branches based on the main branch used for the
current release. Any changes required for a new feature or defect fix are
committed to that feature branch.
- These changes must be covered under 1) a unit test where possible, or 2)
integration tests.
- Integration tests are required if unit tests cannot reliably exercise all
facets of the change.
- Developers are strongly encouraged to follow the
commit message conventions suggested by GitHub.
- Commit messages should be wrapped to 72 characters.
- Commit messages should be written in the present tense. This convention
matches up with commit messages generated by commands like git merge and
git revert.
- Once the feature and corresponding tests are complete, a pull request will be
created using the GitHub/GitLab web interface. The pull request should
indicate which feature or defect is being addressed and should provide a
high-level description of the changes made.
- Code reviews are performed as part of the pull request procedure. Once a
change is ready for review, the author(s) will notify other engineers using
an appropriate mechanism, typically via an
@channel
message in Slack.
- Other engineers will review the changes, using the guidelines above.
- Engineers should note all potential issues with the code; it is the
responsibility of the author(s) to address those issues or explain why they
are not applicable.
- If the feature or defect interacts with PHI or PII, or controls access to
data potentially containing PHI or PII, the code changes must be reviewed by
two members of Fox and Geese's Blue Team (software security team) before the
feature is marked as complete.
- The Blue Team members will provide a security analysis of features to
ensure they satisfy Fox and Geese's compliance and security commitments.
- This review must include a security analysis for potential vulnerabilities
such as those listed in the
OWASP Top 10 or the
CWE top 25.
- This review must also verify that any actions performed by authenticated
users will generate appropriate audit log entries.
- Blue Team members are required to undergo annual training on identifying
the most common software vulnerabilities and will receive ongoing training
on Fox and Geese's compliance and security requirements.
- Once the review process finishes, each reviewer should leave a comment on the
pull request saying "looks good to me" (often abbreviated as "LGTM"), at
which point the original author(s) may merge their change into the release
branch.
Software Release Procedures
- Software releases are treated as changes to existing systems and thus follow
the procedure described in
Configuration Management Policy.